Piper Morgan Roadmap - Sprint A7 Active (Expanded Scope)

Version: 10.0 Last Updated: October 22, 2025, 3:30 PM PDT Key Change: Sprint A6 complete, Sprint A7 expanded to 12 issues (4 categories), Sprint A8 added for Alpha prep

Vision Statement

To create the world’s most advanced AI-assisted development platform, enabling teams to build software with unprecedented intelligence, efficiency, and quality.


πŸ› The Inchworm Protocol

Our Execution Methodology: Complete each epic 100% before moving to next. NO EXCEPTIONS.

Critical Principle: Even when we discover work is partially done (like the production handlers), we VERIFY everything systematically. No assumptions, no skipping.


Current Status (October 22, 2025)

βœ… Completed Work

Phase 1: The Great Refactor (Sept 20 - Oct 8)

All GREAT epics complete with 99%+ verification

Phase 2: Complete the Build of CORE

Sprint A1: Critical Infrastructure βœ… (Oct 8-11)

CORE-CRAFT Superepic βœ… (Oct 11-14)

Sprint A2: Notion & Errors βœ… (Oct 15-16)

Sprint A3: Core Activation βœ… (Oct 17-19)

Sprint A4: Standup Epic βœ… (Oct 19-20)

Sprint A5: Learning System βœ… (Oct 20-21)

Sprint A6: User Infrastructure βœ… (Oct 9-22)

Test Coverage: 100% passing across all sprints (250+ tests) Security: JWT blacklist, keychain integration, audit trail, SSL/TLS Performance: 602K req/sec sustained, <100ms API response

πŸ”„ Currently Active

Position: Sprint A7 (Polish & Buffer) Sprint: A7 of 8 (penultimate Alpha sprint)


CORE Completion Path - Sprints A7-A8

Sprint A7: Polish & Buffer ➑️ (Oct 22-26)

Current Sprint - Expanded scope (12 issues across 4 categories)

1. CORE-UX (4 issues):

2. Critical Fixes (2 issues):

3. CORE-KEYS (3 issues):

4. CORE-ALPHA (3 issues):

Total: 12 issues, 20-29 hours estimated Actual Duration: 1-2 days (based on 88% velocity pattern from Sprint A6) Execution Order: See /dev/active/sprint-a7-gameplan-polish-buffer.md


Sprint A8: Alpha Prep & Launch ⏳ (Oct 27 - Nov 1)

Next Sprint - Final Alpha sprint before Wave 2 launch

Testing & Validation:

Documentation:

Alpha Deployment:

Baseline Piper Education (demoted from Phase 3, 90% complete):

Estimated Duration: 3-5 days Target: Alpha Wave 2 launch readiness


Alpha Milestone Completion Analysis

βœ… Completed Sprints (6 of 8)

Total Delivered: 32 issues, 54 issues closed in Alpha milestone overall

πŸ”œ Remaining Work (Sprints A7-A8)

Sprint A7: Polish & Buffer (12 issues, 20-29 hours):

Sprint A8: Alpha Prep & Launch (activities, 3-5 days):

Total Remaining: 12 issues + A8 activities Estimated Completion: Early November 2025


Post-Alpha Path

Phase 3: Alpha Testing v0.1 (Early November 2025)

Status: Ready to begin after Sprint A8

Phase 4: MVP Completion (Nov-Dec 2025)

What MVP Needs (from VALID-2 assessment):

Already Implemented (70-75% complete):

Configuration Required (1 week):

Testing Required (1 week):

Polish Required (1 week):

MVP Features to Validate: All originally planned features still need verification:

Phase 5: Beta Testing v0.9 (December 2025)

Phase 6: Launch v1.0 (January 2026)


Critical Insights from CRAFT

What Changed Our Understanding

  1. Handlers aren’t placeholders - 22 production implementations exist
  2. MVP closer than expected - 70-75% complete vs assumed 40%
  3. Learning already started - Pattern learning handler exists
  4. Standup partially done - Handler exists, needs wiring

What DOESN’T Change

  1. Alpha plan execution - All A2-A7 items get verified
  2. No skipping - Even if handlers exist, we verify everything
  3. Quality standards - 100% completion required
  4. Inchworm protocol - Sequential, methodical progress

Timeline Summary

October 2025: βœ… Mostly Complete

Early November 2025:

Mid-Late November 2025:

December 2025:

January 2026:


Success Metrics

CORE Completion βœ… (October 22, 2025)

Alpha Success Criteria (Early November 2025)

MVP Launch (December 2025)


Risk Management

Mitigated Risks βœ…

Active Risks

Mitigation Strategy


Key Principle: Trust but Verify

CRAFT showed us that much more is implemented than we knew. This is fantastic! But we still:

  1. Verify every Alpha checklist item
  2. Test every integration point
  3. Document every gap
  4. Complete every sprint fully

The handlers existing means sprints might go faster, not that we skip verification.


This roadmap reflects the remarkable progress through Sprint A6, with Sprint A7 expanded to 12 issues and Sprint A8 added for Alpha prep. Quality and completeness continue to determine pace, not arbitrary deadlines.

Version: 10.0 Last Updated: October 22, 2025, 3:30 PM PDT Next Update: After Sprint A7 completion or Sprint A8 start Previous: v9.0 (Oct 22, 2025, 1:45 PM) - Sprint A6 Complete